(UMM)

Affected Unit Published Date/Time Event Type Event Status Event Start Date/Time (GMT) Event End Date/Time (GMT) Available Capacity Cause Related Information
E_LYNE3 27/05/2021
02:13AM
Unplanned Production unavailability - Active 27/05/2021
02:30AM
27/05/2021
04:00AM
123 Milling Plant
E_LYNE3 27/05/2021
02:13AM
Unplanned Production unavailability - Active 26/05/2021
04:30AM
27/05/2021
02:30AM
130 Plant Available
E_LYNE3 27/05/2021
02:13AM
Unplanned Production unavailability - Active 27/05/2021
04:00AM
27/05/2021
12:30PM
130 Plant Available
E_LYNE3 26/05/2021
04:23AM
Unplanned Production unavailability - Active 26/05/2021
02:00AM
26/05/2021
04:30AM
126 Plant Available
E_LYNE3 26/05/2021
03:18AM
Unplanned Production unavailability - Active 26/05/2021
01:00AM
26/05/2021
02:00AM
126 Milling Plant
E_LYNE3 26/05/2021
02:13AM
Unplanned Production unavailability - Active 25/05/2021
11:00AM
26/05/2021
01:00AM
130 Plant Available
E_LYNE3 25/05/2021
12:18PM
Unplanned Production unavailability - Active 25/05/2021
02:30AM
25/05/2021
11:00AM
130 Plant Available
E_LYNE3 25/05/2021
02:28AM
Unplanned Production unavailability - Active 25/05/2021
00:30AM
25/05/2021
01:00AM
120 Milling Plant
E_LYNE3 25/05/2021
02:28AM
Unplanned Production unavailability - Active 25/05/2021
01:00AM
25/05/2021
02:30AM
128 Plant Available
E_LYNE3 25/05/2021
01:53AM
Unplanned Production unavailability - Active 21/05/2021
14:30PM
25/05/2021
00:30AM
130 Plant Available
E_LYNE3 16/05/2021
12:48PM
Unplanned Production unavailability - Active 16/05/2021
10:30AM
16/05/2021
11:30AM
117 Plant Available
E_LYNE3 16/05/2021
12:48PM
Unplanned Production unavailability - Active 16/05/2021
11:30AM
17/05/2021
13:00PM
130 Plant Available
E_LYNE3 16/05/2021
11:38AM
Unplanned Production unavailability - Active 16/05/2021
10:30AM
16/05/2021
11:30AM
105 Milling Plant
E_LYNE3 11/05/2021
17:18PM
Unplanned Production unavailability - Active 11/05/2021
16:00PM
14/05/2021
17:30PM
130 Plant Available
E_LYNE3 08/05/2021
17:53PM
Unplanned Production unavailability - Active 09/05/2021
22:00PM
10/05/2021
11:00AM
130 Plant Available
E_LYNE3 08/05/2021
17:53PM
Unplanned Production unavailability - Active 08/05/2021
16:30PM
09/05/2021
22:00PM
130 Plant Available
E_LYNE3 08/05/2021
17:53PM
Unplanned Production unavailability - Active 08/05/2021
15:30PM
08/05/2021
16:30PM
129 Plant Available
E_LYNE3 08/05/2021
16:38PM
Unplanned Production unavailability - Active 08/05/2021
14:30PM
08/05/2021
15:30PM
127 Milling Plant
E_LYNE3 08/05/2021
15:39PM
Unplanned Production unavailability - Active 08/05/2021
13:30PM
08/05/2021
14:30PM
130 Plant Available
E_LYNE3 08/05/2021
09:38AM
Unplanned Production unavailability - Active 07/05/2021
13:30PM
08/05/2021
09:00AM
0 Plant Available
E_LYNE3 08/05/2021
09:38AM
Unplanned Production unavailability - Active 08/05/2021
09:00AM
08/05/2021
13:30PM
0 Plant Available
E_LYNE3 07/05/2021
15:18PM
Unplanned Production unavailability - Active 07/05/2021
15:00PM
07/05/2021
19:00PM
0 Plant Available
E_LYNE3 07/05/2021
15:18PM
Unplanned Production unavailability - Dismissed 07/05/2021
17:00PM
07/05/2021
18:00PM
0 Plant Available Event automatically withdrawn.
E_LYNE3 07/05/2021
14:43PM
Unplanned Production unavailability - Active 07/05/2021
10:00AM
07/05/2021
13:30PM
0 Boiler
E_LYNE3 05/05/2021
15:53PM
Unplanned Production unavailability - Active 05/05/2021
00:00AM
07/05/2021
10:00AM
0 Boiler
E_LYNE3 05/05/2021
08:53AM
Unplanned Production unavailability - Dismissed 05/05/2021
22:00PM
06/05/2021
20:00PM
130 Plant Available Event automatically withdrawn.
E_LYNE3 04/05/2021
22:33PM
Unplanned Production unavailability - Active 04/05/2021
22:00PM
05/05/2021
00:00AM
95 Milling Plant
E_LYNE3 04/05/2021
22:33PM
Unplanned Production unavailability - Active 02/05/2021
18:30PM
04/05/2021
22:00PM
130 Plant Available

Planned Outages

Asset ID Available Capacity (MW) Start Date (GMT) End Date (GMT)
Show Archive

Static Data

Asset ID Normal Capacity (MW) Fuel Type Location Market
E_LYNE3 133 Biomass Lynemouth Power GB BETTA Market