Affected Unit Published Date/Time Event Type Event Status Event Start Date/Time (GMT) Event End Date/Time (GMT) Available Capacity Cause Related Information
E_LYNE1 01/06/2025
13:58PM
Unplanned Production unavailability - Active 01/06/2025
05:00AM
01/06/2025
16:30PM
82 Plant Available
E_LYNE2 02/06/2025
13:13PM
Unplanned Production unavailability - Active 02/06/2025
07:00AM
02/06/2025
23:00PM
105 Plant Available

Planned Outages

Asset ID Available Capacity (MW) Start Date (GMT) End Date (GMT)

Static Data

Asset ID Normal Capacity (MW) Fuel Type Location Market
E_LYNE1 133 Biomass Lynemouth Power GB BETTA Market
E_LYNE2 133 Biomass Lynemouth Power GB BETTA Market
E_LYNE3 133 Biomass Lynemouth Power GB BETTA Market