| T_LAGA-1 |
18/09/2026 23:14PM |
Planned |
Production unavailability - Active |
17/09/2026 22:00PM |
18/09/2026 22:30PM |
400 |
Commissioning - Variable Output |
Unit remains unavailable while commissioning activities are completed following a major outage. Intermittent gas turbine starts, synchronisations and generation exports may occur during this period for testing purposes. Export levels may vary between 0 MW and approximately 400 MW during commissioning activities. The unit should not be considered commercially available until commissioned. |
| T_LAGA-1 |
16/09/2026 10:08AM |
Planned |
Production unavailability - Active |
16/09/2026 08:00AM |
17/09/2026 22:00PM |
0 |
Planned Outage |
Whole station outage extension for HRSG12 repair back to pressure tight to enable single unit running on Unit 11. |
| T_LAGA-1 |
15/09/2026 09:53AM |
Planned |
Production unavailability - Active |
15/09/2026 08:00AM |
16/09/2026 08:00AM |
0 |
Planned Outage |
Whole station outage. GT11 OTC investigation. |
| T_LAGA-1 |
14/09/2026 09:38AM |
Planned |
Production unavailability - Active |
14/09/2026 08:00AM |
14/09/2026 11:00AM |
0 |
Planned Outage |