(UMM)

Affected Unit Published Date/Time Event Type Event Status Event Start Date/Time (GMT) Event End Date/Time (GMT) Available Capacity Cause Related Information
T_LAGA-1 27/06/2020
22:29PM
Unplanned Completed 27/06/2020
22:28PM
27/06/2020
23:00PM
905 Outage Ends
T_LAGA-1 26/06/2020
20:51PM
Unplanned Superseded 26/06/2020
21:00PM
27/06/2020
23:00PM
400 Electrical
T_LAGA-1 26/06/2020
17:49PM
Unplanned Superseded 26/06/2020
17:48PM
26/06/2020
22:00PM
0 Electrical
T_LAGA-1 26/06/2020
16:58PM
Unplanned Ongoing 26/06/2020
16:57PM
26/06/2020
19:00PM
15 Electrical
T_LAGA-1 21/06/2020
23:38PM
Unplanned Completed 21/06/2020
23:59PM
22/06/2020
00:30AM
819 Outage Ends
T_LAGA-1 21/06/2020
16:40PM
Unplanned Ongoing 21/06/2020
16:39PM
22/06/2020
00:30AM
400 Boiler
T_LAGA-1 14/06/2020
14:27PM
Planned Future 15/06/2020
08:00AM
15/06/2020
14:00PM
816 Plant Testing - Variable Output ST18 Flux Testing.
T_LAGA-1 14/06/2020
10:00AM
Planned Completed 14/06/2020
10:00AM
14/06/2020
11:00AM
800 Gas Turbine
T_LAGA-1 13/06/2020
15:54PM
Planned Superseded 14/06/2020
03:00AM
14/06/2020
11:00AM
400 Gas Turbine
T_LAGA-1 13/06/2020
15:29PM
Planned Superseded 14/06/2020
03:00AM
14/06/2020
11:00AM
807 Gas Turbine
T_LAGA-1 13/06/2020
15:10PM
Planned Future 13/06/2020
23:30PM
14/06/2020
12:00PM
400 Gas Turbine
T_LAGA-1 12/06/2020
13:16PM
Unplanned Ongoing 12/06/2020
13:12PM
12/06/2020
19:00PM
366 Gas Turbine
T_LAGA-1 09/06/2020
15:16PM
Unplanned Ongoing 09/06/2020
15:15PM
09/06/2020
17:15PM
90 Steam Turbine
T_LAGA-1 08/06/2020
17:23PM
Unplanned Completed 08/06/2020
17:21PM
09/06/2020
12:00PM
815 Steam Turbine
T_LAGA-1 08/06/2020
10:56AM
Unplanned Ongoing 08/06/2020
10:56AM
09/06/2020
12:00PM
0 Steam Turbine
T_LAGA-1 08/06/2020
08:14AM
Unplanned Ongoing 08/06/2020
08:13AM
08/06/2020
14:00PM
0 Steam Turbine
T_LAGA-1 08/06/2020
05:51AM
Unplanned Ongoing 08/06/2020
05:56AM
08/06/2020
10:00AM
0 Steam Turbine
T_LAGA-1 06/06/2020
13:35PM
Planned Completed 06/06/2020
14:00PM
07/06/2020
23:00PM
801 Early end to planned outage
T_LAGA-1 03/06/2020
12:07PM
Planned Completed 07/06/2020
23:00PM
08/06/2020
23:00PM
801 Early end to planned outage
T_LAGA-1 29/05/2020
15:10PM
Planned Completed 08/06/2020
23:00PM
10/06/2020
23:00PM
801 Early end to planned outage

Planned Outages

Asset ID Available Capacity (MW) Start Date (GMT) End Date (GMT)
T_LAGA-1 0 17/05/2024
22:00PM
02/08/2024
22:00PM
T_LAGA-1 0 18/04/2025
23:00PM
04/05/2025
23:00PM
Show Archive

Static Data

Asset ID Normal Capacity (MW) Fuel Type Location Market
T_LAGA-1 905 Fossil Gas Plymouth GB BETTA Market