(UMM)

Affected Unit Published Date/Time Event Type Event Status Event Start Date/Time (GMT) Event End Date/Time (GMT) Available Capacity Cause Related Information
T_LAGA-1 30/01/2021
22:19PM
Unplanned Completed 30/01/2021
22:30PM
30/01/2021
23:30PM
400 Boiler
T_LAGA-1 30/01/2021
16:13PM
Unplanned Superseded 30/01/2021
18:30PM
30/01/2021
23:30PM
0 Boiler
T_LAGA-1 30/01/2021
13:31PM
Unplanned Ongoing 30/01/2021
13:30PM
30/01/2021
18:30PM
0 Boiler
T_LAGA-1 29/01/2021
13:22PM
Unplanned Completed 29/01/2021
13:30PM
29/01/2021
21:00PM
400 Boiler
T_LAGA-1 29/01/2021
08:26AM
Unplanned Superseded 29/01/2021
18:00PM
29/01/2021
21:00PM
0 Boiler
T_LAGA-1 29/01/2021
07:51AM
Unplanned Superseded 29/01/2021
13:00PM
29/01/2021
18:00PM
0 Boiler
T_LAGA-1 29/01/2021
03:35AM
Unplanned Ongoing 29/01/2021
04:00AM
29/01/2021
13:00PM
0 Boiler
T_LAGA-1 28/01/2021
16:25PM
Unplanned Superseded 28/01/2021
18:00PM
29/01/2021
04:00AM
0 Boiler
T_LAGA-1 28/01/2021
15:21PM
Unplanned Ongoing 31/01/2021
23:00PM
03/02/2021
23:00PM
400 Boiler
T_LAGA-1 21/01/2021
11:07AM
Unplanned Ongoing 24/01/2021
23:00PM
31/01/2021
23:00PM
400 Boiler
T_LAGA-1 16/01/2021
12:28PM
Unplanned Superseded 17/01/2021
23:00PM
24/01/2021
23:00PM
400 Boiler
T_LAGA-1 12/01/2021
04:27AM
Unplanned Completed 12/01/2021
05:30AM
12/01/2021
06:30AM
400 Gas Turbine
T_LAGA-1 12/01/2021
02:24AM
Unplanned Ongoing 12/01/2021
03:30AM
12/01/2021
06:30AM
0 Gas Turbine Rotor barring motor.
T_LAGA-1 11/01/2021
23:08PM
Unplanned Ongoing 11/01/2021
23:15PM
12/01/2021
03:15AM
0 Gas Turbine
T_LAGA-1 07/01/2021
16:31PM
Planned Future 08/01/2021
23:30PM
11/01/2021
23:00PM
0 Auxillary Plant Repairs to ACC
T_LAGA-1 07/01/2021
10:43AM
Unplanned Completed 07/01/2021
11:00AM
07/01/2021
11:30AM
400 Steam Turbine
T_LAGA-1 07/01/2021
09:36AM
Unplanned Ongoing 07/01/2021
09:36AM
07/01/2021
11:30AM
50 Steam Turbine
T_LAGA-1 04/01/2021
22:20PM
Unplanned Completed 04/01/2021
22:30PM
04/01/2021
23:00PM
390 Outage Ends
T_LAGA-1 04/01/2021
19:26PM
Unplanned Superseded 04/01/2021
19:30PM
04/01/2021
23:00PM
0 Steam Turbine
T_LAGA-1 04/01/2021
19:20PM
Unplanned Ongoing 04/01/2021
19:30PM
04/01/2021
23:00PM
210 Steam Turbine
T_LAGA-1 04/01/2021
14:58PM
Unplanned Ongoing 08/01/2021
23:00PM
17/01/2021
23:00PM
400 Cooling System
T_LAGA-1 03/01/2021
15:29PM
Unplanned Ongoing 03/01/2021
16:00PM
08/01/2021
23:00PM
400 Boiler
T_LAGA-1 03/01/2021
15:24PM
Planned Completed 03/01/2021
15:30PM
03/01/2021
23:00PM
824 Early end to planned outage
T_LAGA-1 30/12/2020
09:49AM
Planned Future 02/01/2021
02:00AM
03/01/2021
23:00PM
0 Planned Outage

Planned Outages

Asset ID Available Capacity (MW) Start Date (GMT) End Date (GMT)
T_LAGA-1 0 17/05/2024
22:00PM
02/08/2024
22:00PM
T_LAGA-1 0 18/04/2025
23:00PM
04/05/2025
23:00PM
Show Archive

Static Data

Asset ID Normal Capacity (MW) Fuel Type Location Market
T_LAGA-1 905 Fossil Gas Plymouth GB BETTA Market